Current context: In a significant development for Arunachal Pradesh’s energy sector, the Satluj Jal Vidyut Nigam (SJVN) Limited has released ₹269.98 crore as land compensation for the Etalin Hydroelectric Project (HEP).
Project Overview:
- Location: Dibang Valley, Arunachal Pradesh
- Capacity: 3,097 MW
- Components: Two dams on the Dri and Tangon (Talo) rivers, and an underground powerhouse complex
Community Engagement:
- Affected Communities: Idu Mishmi tribe
- Concerns: Displacement, loss of ancestral land, and environmental impacts
- Initiatives: Establishment of a Community Conservation Area to protect biodiversity and cultural heritage
Environmental Considerations:
- Biodiversity Impact: Project area located in a biodiversity hotspot; previous Environmental Impact Assessments deemed inadequate
- Regulatory Oversight: Forest Advisory Committee (FAC) has declined forest clearance in its current form; recommends reassessment and revised proposals