October 5, 2025
  • Satluj Jal Vidyut Nigam (SJVN) will invest around Rs 1.5 lakh crore over the next 7-8 years in various power projects within and outside the country. The power giant will make this investment to achieve its targeted installed capacity of 25,000 MW by 2030.
  • The SJVN said the work on the Sunni Dam Hydroelectric Project, around 40 km from Shimla, will start in a month’s time. The project with 382 MW capacity will cost around Rs 2,600 crore.
  • All formalities have been completed and clearances received. The investment approval from the Centre is expected in the next 15 days. The work on the project will start in a month’s time, and the project will be commissioned in five years,” said SJVN chairman and Managing Director Nand Lal Sharma.
  • The work on hydroelectric plants in the state – 210 MW Luhri Stage 1 and the 66 MW Dhaulasidh project – was on at war footing. “These projects were declared unviable but SJVN has made them viable and these will be commissioned by 2024-25.
  • The SJVN would invest around Rs 1.5 lakh crore over the next 7-8 years, mainly in renewable sources like solar and wind, to achieve its revised and upscaled target of becoming a 25,000 MW company by 2030.
  • The company’s current installed capacity is 2,016 MW.
  • SJVN has 14 projects under construction within and outside the country with a capacity of around 4,500 MW.
  • SJVN has provided employment to around 15,000 people directly and indirectly.